PRINCE2 PRINCE2-Agile-Foundation Dumps - PRINCE2 Agile Foundation Exam PDF Sample Questions

discount banner
Exam Code:
PRINCE2-Agile-Foundation
Exam Name:
PRINCE2 Agile Foundation Exam
92 Questions
Last Update Date : 15 April, 2024
PDF + Test Engine
$60 $78
Test Engine Only
$50 $65
PDF Only Demo
$35 $45.5

PRINCE2 PRINCE2-Agile-Foundation This Week Result

0

They can't be wrong

0

Score in Real Exam at Testing Centre

0

Questions came word by word from this dumps

Best PRINCE2 PRINCE2-Agile-Foundation Dumps - pass your exam In First Attempt

Our PRINCE2-Agile-Foundation dumps are better than all other cheap PRINCE2-Agile-Foundation study material.

Only best way to pass your PRINCE2 PRINCE2-Agile-Foundation is that if you will get reliable exam study materials. We ensure you that realexamdumps is one of the most authentic website for PRINCE2 PRINCE2 Agile exam question answers. Pass your PRINCE2-Agile-Foundation PRINCE2 Agile Foundation Exam with full confidence. You can get free PRINCE2 Agile Foundation Exam demo from realexamdumps. We ensure 100% your success in PRINCE2-Agile-Foundation Exam with the help of PRINCE2 Dumps. you will feel proud to become a part of realexamdumps family.

Our success rate from past 5 year very impressive. Our customers are able to build their carrier in IT field.

Owl
Search

45000+ Exams

Buy

Desire Exam

Download

Exam

and pass your exam...

Related Exam

Realexamdumps Providing most updated PRINCE2 Agile Question Answers. Here are a few exams:


Sample Questions

Realexamdumps Providing most updated PRINCE2 Agile Question Answers. Here are a few sample questions:

PRINCE2 PRINCE2-Agile-Foundation Sample Question 1

Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.

2. It should identify the minimum viable product and when it will be delivered.

3. It should take into account that the scope may be reduced during the course of the project.

4. It should show the features, the order in which they will be delivered and any dependencies.


Options:

A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4

Answer: C

PRINCE2 PRINCE2-Agile-Foundation Sample Question 2

Which statement about the waterfall methodology definition is CORRECT?


Options:

A. It states that deadlines should not be moved
B. It has distinct goals for each stage of development
C. It is a behavior that involves making things transparent
D. It promotes the use of experiments carried out in a scientific way

Answer: B Explanation: Reference: [Reference: https://www.lucidchart.com/blog/agile-vs-waterfall-vs-kanban-vs-scrum, ]

PRINCE2 PRINCE2-Agile-Foundation Sample Question 3

What should be decided when configuring PRINCE2 effectively?


Options:

A. What to remove and where to add guidance
B. Where to put the emphasis and where to add guidance
C. What to significantly change to create the right blend
D. Which areas are not enabled to work with agile

Answer: D

PRINCE2 PRINCE2-Agile-Foundation Sample Question 4

Why are team working agreement produced?


Options:

A. To create structure so that the team manager can assess individual performance
B. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
C. To make the team rules visible to the project manager for monitoring purposes
D. To ensure that the delivery team members comply with company policy

Answer: B Explanation: Explanation: Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126 &showNav=true&expandNav=truf